Park East Boulevard
Location
Lafayette, IN
Client
City of Lafayette
Project Dates
April 2024- December 2025
Type of Work
Public
Services
GPS Site Grading
Scope
Atlas installed 7,000 linear feet of water main, 13,000 linear feet of storm sewer, and 9,000 linear feet of deep sanitary sewer. Excavations reached depths of up to 30 feet in challenging wet, muddy soils across farmland and swamp. To stabilize the site, we deployed GPS-controlled equipment for precise grading and utility installation.
Unique Challenges
With both farmland and swamp, the site was wet and muddy, making the project especially demanding. Our crews set wellpoints throughout the corridor and ran pumps continuously to keep excavations dry. The Atlas 850 excavator handled the toughest digs, allowing us to push through difficult conditions and deliver critical infrastructure safely and efficiently.